Timeline

Second Quarter of 2020

Proof of possibility

Obtaining Government consent to begin the project

Second Quarter of 2020

Third Quarter of 2020

Getting Permits

  • Company Permits
  • Land certificate
  • Building permit (Izin Membangun)
  • Local permit (Izin Local)
  • KITAS (visa and work permit)
Third Quarter of 2020

Fourth Quarter of 2020

First Stage

Construction of the first stage buildings and infrastructure

time window: 2 months preperation, 3 months construction and 1 month finishing (total: 6 months)

Fourth Quarter of 2020

Second Quarter of 2021

Start of Operation

Opening of the accommodations

Opening of the English school and other intern teachings of employees.

At least a half season is needed to obtain proof of the project.

Analysis of the results and further planing

Second Quarter of 2021

Third Quarter of 2021

Preparation for the Second Stage

Analysis of the results and detail planning for the second stage during the end of the season

Getting permits for the second stage

Third Quarter of 2021

Fourth Quarter of 2021

Construction for the Second Stage

During the off season construction of the second stage buildings and infrastructure

Time window: 2 months preperation, 2 months construction and 1 month finishing (total: 5 months)

Fourth Quarter of 2021

Second Quarter of 2022

Second Stage Opening

The second season will be one year of reserve and proof.

Second Quarter of 2022

Second Quarter of 2023

Preparation of the Third Stage

Planning and getting permits for the third stage during the third season.

Second Quarter of 2023

Third Quarter of 2023

Construction of the Third Stage

Time window of construction for the third stage: 8 months during and after the third season.

Third Quarter of 2023

Second Quarter of 2024

Opening of the Third Stage

 Start of operation of the third stage in the fourth season.

Second Quarter of 2024

from 2024

Further Stages

Granted that the necessary permits are obtained, and the first stages work as planned, the project will further be expanded. Since our passion is to build with bamboo, we will always construct new building projects on Lemaina and the region of Mulut Seribu. These projects will be financed by the profit from the last years of operation and further foreign and domestic investments.

from 2024